Official inauguration by 2011-02-03
His Excellency President Hifikepunye Pohamba
First cement production 2010-12-08
First clinker production 2010-11-28
Securing gypsum supply from Elpse Minerals 2010-08-25
Securing iron ore supply from Okorusu 2010-08-12
Switch over from 11kV to 132 kV power supply 2010-08-12
First group of recruits sent to Germany for training 2010-04-27
First blast in quarry 2010-03-25
Roof wetting celebration 2010-02-04
Signing of agreement with TransNamib 2009-12-16
to construct private siding
Groundbreaking ceremony 2009-01-29
Start of construction of the Ohorongo cement plant 2009-01-01
Arrival of cement from Schwenk for plant construction 2008-12-08
Starting work on access road 2008-08-28
Milestone event in Windhoek 2008-08-13
Turn-key contract with Polysius 2008-07-14
Final business decision 2008-07-08
Issue of Mining Licence No. 153 2008-07-06
Environmental Impact Assessment & 2008-02-13
Environmental Management Plan
Geological resource calculation report 2008-02-10
Public participation process & public meetings 2007-09-20
Founding of Ohorongo 2006-06-03
Purchasing of EPL 3371 from Ongopolo 2006-05-19
Diamond core drilling - 12 boreholes with 1090m 2006-03-12
Date of issue of EPL (holder - Ongopolo) 2005-11-25
700,000 tons of cement per year
N$ 2.5 billion
300 years